North Course Update

North Course Construction: Designing for Climate Resilience


DESIGN

RTJII design work near completion.


SITE WORK

Holes 10 & 11: Sodding complete

Holes 12-18: Prep work underway


REPAIRS

Main line drainage & culverts under repair in various spots.


PERMITTING

Awaiting permit approval to meet updated FEMA flood zone regulations.


HYDROLOGY STUDY

Working with the City's Public Works Department to study site hydrology and co-design critical flood management solutions.


LOOKING AHEAD

Irrigation & grading work on holes 12-18 scheduled to start Spring 2024 after permits are re-issued and hydrology study is complete.


COMPLETION

On track for WINTER 2024 completion.