North Course Construction: Designing for Climate Resilience
MARCH 2024
PERMITS
The final permit with updated FEMA flood zone regulations was approved on March 25.
PREPARATION
The design and construction team, including the contractor and shaper are mobilizing over the next six weeks.
CONSTRUCTION
Irrigation and grading on the remaining 7 holes are scheduled to begin in early May.
FLOOD MITIGATION
We will continue to work with Public Works on upgrading existing infrastructure for stormwater retention.
SITE WORK
HOLES 12-18 (May to August)
Work on the remaining 7 holes will last 4 months, starting with holes 16 & 17.
SODDING (August to September)
Sodding will follow and last 2 months.
FINISHING WORK (September to December)
Additional landscaping and final touches will take place during the fourth quarter of the year.
COMPLETION (December 2024)
The project remains on track for a December 2024 completion.
OCTOBER 2023
DESIGN
The design team has selected a shaper and is ready to begin shaping once the permit renewal is secured.
SITE WORK
Newly sodded holes 10 & 11 are settling in nicely.
PERMITS
City's Public Works Department will be reviewing our submission for permit renewal with updated FEMA flood zone regulations.
We anticipate permit approval by year-end.
CONSTRUCTION
Irrigation & grading work on holes 12-18 scheduled to start SPRING 2024 after permits are re-issued and any inclement weather clears.
STORM MANAGEMENT
We continue to work with the City's Public Works Department to clean, replace, and upgrade drainage culverts in preparation for the future storms.
We will continue to study site hydrology and co-design critical flood management solutions with the City as part of our comprehensive storm management plan.
COMPLETION
Remain on track for a DECEMBER 2024 completion.
AUGUST 2023
DESIGN
RTJII design work near completion.
SITE WORK
Holes 10 & 11: Sodding complete
Holes 12-18: Prep work underway
REPAIRS
Main line drainage & culverts under repair in various spots.
PERMITTING
Awaiting permit approval to meet updated FEMA flood zone regulations.
HYDROLOGY STUDY
Working with the City's Public Works Department to study site hydrology and co-design critical flood management solutions.
LOOKING AHEAD
Irrigation & grading work on holes 12-18 scheduled to start Spring 2024 after permits are re-issued and hydrology study is complete.
COMPLETION
On track for WINTER 2024 completion.